Background
How we got the data
Where this came from
CIRCUI-T was built for a Naval War College tabletop exercise on data center warfare: what happens to compute, and to the people who depend on it, when the utilities behind it are attacked or cut off. The exercise runs facilitated groups through a contested scenario in about ninety minutes, and it needs an instrument that can answer "what breaks, and when" from a fixed, inspectable set of assumptions rather than from a facilitator's intuition.
Two research questions
How exposed are the Tainan compute and fab cluster, and its military-usable compute and bandwidth, to an LNG blockade, kinetic strikes, cyber degradation and submarine cable cuts over an ILLUSTRATIVE 90-day horizon?
What changes when the user adds hypothetical facilities, such as small modular and micro reactors, new data center classes and satellite gateways? Each is labeled ILLUSTRATIVE or SIMULATED.
Why Tainan
The Southern Taiwan Science Park in Tainan holds advanced TSMC fabs alongside UMC and Innolux sites, all within reach of the same 345 and 161 kV transmission, the same reservoirs and reclaimed-water plants, and the same submarine cable landing at Fangshan. The gas plants that carry much of the load, Sun Ba on the park's doorstep and Hsinta to the south, burn LNG that arrives by sea at Yong-An. A fab is a compute customer of a particular kind, and a data center placed next to one shares its utilities and its exposure. That makes the cluster a compact place to ask the exercise's question, with enough public data to build from and enough gaps to be plain about.
Some facts about it are firm. Taiwan's statutory LNG safety stock is 11 days in 2025, rising to 14 in 2027, with storage requirements of 20 and 24 days (Ministry of Economic Affairs). Natural gas produced 47.7 percent of Taiwan's electricity in 2025 (Energy Administration, 2025 Energy Statistics Handbook, table 3-01). Sun Ba Phase I is rated 980 MW in two 490 MW units (NS Energy, Sun Ba II Power Plant, 30 September 2021). The September 2026 OpenStreetMap pull also carries 980 MW for way 151212447. TSMC's reported water use at the park is 120,000 m³ per day (TSMC). Taiwan has had no operating nuclear generation since 17 May 2025 (Taipower).
Others are not, and the scenario says so. Sun Ba II at 1,100 MW is placed at the same campus as a SIMULATED addition and switched off by default because its commercial date is unconfirmed. Hsinta's gas share, 3,526 MW, comes from Taipower's unit table with its coal units treated as a SIMULATED availability. Fab electricity and water loads are SIMULATED shares of corporate totals, never a per-fab rating. The grid connections themselves are a logical completion of incomplete public mapping.
Connectivity beyond the ground
The exercise asked about space and about what comes after 5G. Taiwan's regulatory position moved in 2025 and 2026: the satellite-operator foreign-ownership exemption passed on 21 July 2026; Chunghwa Telecom holds OneWeb (June 2025) and SES O3b mPOWER (November 2025) licenses and signed a gateway memorandum in January 2026; the digital ministry counts 773 non-terrestrial network sites; the space agency plans a LEO demonstration in 2027. CIRCUI-T models this as objects on the existing data network: a constellation off the map, a space gateway, satellite terminals at facilities, and wireless backhaul links inside the park. Capacities are SIMULATED from published anchors: SES quotes 40 Mbps to 10 Gbps per terminal and up to 1.8 Gbps to a land site; SpaceX launches about 2.7 Tbps per V2 Mini batch; OneWeb about 7 Gbps per satellite; Ericsson's E-band radios carry 10 to 25 Gbps over 2 to 3 km. Jamming is modeled as link damage. Direct-to-device 6G is a discussion card in the exercise, not a modeled object.
What the instructor's facility list became
The exercise brief named five data center classes. They appear in the terminal as one-click templates with the source on the card: enterprise (PUE 1.6, from the IEA's 1.5 to 1.7 range), co-location (Equinix 2024 fleet PUE 1.39), cloud hyperscale (Google 2024 fleet PUE 1.09), AI hyperscale (EPRI 2024 on 100 to 1,000 MW campuses), and a super-intelligence class that is SIMULATED because no operating figures are published. Beside them sit generation and storage options from the reading list: SMR-300 and SMR-77, a 5 MW microreactor, a 20 MW military microreactor (EIA, April 2026), a fuel cell class (Bloom, 325 kW per unit), a self-powered gas campus at 1.3 to 1.7 times demand (IEA), a grid battery block (Tesla Megapack 2 XL) and a microgrid composite with a point-of-common-coupling switch (Hirsch, Parag and Guerrero, 2018). Every value is ILLUSTRATIVE or SIMULATED and every card says which.
Every citation behind these figures is listed on the Tainan scenario sources page.
Honesty and model boundaries
Every modeled number is tied to a cited source or flagged SELF-DERIVED, ILLUSTRATIVE or SIMULATED. What we cannot measure is stated as a finding.
The model shows relative and structural exposure and does not predict real outcomes. Hypothetical facilities and their capacities, reactors included, are ILLUSTRATIVE or SIMULATED, not claims about existing infrastructure.
The modeled grid is a logical network. Where OpenStreetMap shows no connection, 231 SIMULATED feeders (about 257 km) complete the network, each listed in the scenario's ledger. It is not a one-line diagram, and no line or station rating is asserted without a source.
The solver has no dispatch order, so backup generation runs from day 0: a 48-hour diesel stock is gone by day 2 whether or not the grid is up. Batteries are deferred for the same reason.
Taiwan has had no operating nuclear generation since 17 May 2025 (Taipower shutdown statement, Taipower nuclear plant status). SMRs operate commercially in Russia and China (IAEA SMR Platform booklet).
Fab process loads are SIMULATED shares of corporate totals, never a per-fab rating. No scenario figure is read from the third-party basemap.
How we verify it
Student research and a testing instrument. Results are SIMULATED from flagged inputs; none has been validated against real outcomes or operator data.
See Tech Specs for this build's verification status.
The systems modeled
One network, eight commodities, ninety days
The terminal holds a map of assets (sources, substations, storage, converters, waypoints), lines between them, delivery points, and workloads at those delivery points that demand commodities. Each day it solves a maximum-flow problem for each commodity in turn and records what every workload received. It does this for day 0 through day 90. Damage, repair clocks, stock levels and scheduled events can change the network from day to day, so the model evaluates 91 daily states; when nothing changes, one solve stands for all 91.
The commodities are electric (MW), water (m³ per day), gas (Mcf per day), steam, oil, fuel (gallons), data (Gbps) and compute (IT-MW). Compute is produced by data centers and consumed by workloads, and it travels over modeled compute links between the two, which is how a workload at one delivery point can be served from a campus somewhere else. Compute link capacity is a modeling convention; it is not a claim about any real circuit.
Data centers are converters
A data center is a converter with three inputs and one output. It needs electricity equal to its IT load times its PUE, water set by its WUE and cooling mode, and a data connection. Electricity and data are critical: short them and the compute output falls in proportion. Water is degrading: short it and the output falls to a floor of half, on the assumption that a facility can shed cooling load before it stops. PUE is a lever in three places: on each facility's card, as a scenario-wide multiplier in Settings, and as a preset when you pick a cooling mode. The template defaults run from 1.1 (evaporative, cloud hyperscale) to 1.6 (air, enterprise), and the source for each is on its card.
Assumptions and methods
Stocks and flows
Some commodities flow and some deplete from a stock. Oil and fuel are always stocks; gas becomes one when the scenario says so, and both Tainan scenarios do. A gas plant then draws from Yong-An's modeled inventory every day at its full-output burn (MW times 24 times heat rate, divided by 1.036 MMBtu per Mcf, the EIA's average), and Yong-An is refilled over a named import lane from a source that represents deliveries by sea. Cut the lane and the inventory counts down. The inventory in both scenarios is fixed at eleven days of the real consumers' burn, SELF-DERIVED from the 2025 statutory stock; the 14-day 2027 requirement is disclosed beside it. A second store represents the LNG behind the rest of Taiwan's gas-fired generation, sized the same way, so a national blockade removes the gas share of the grid imports too.
Backup diesel generators carry their fuel on board and burn it at the rated rate from day 0 whether or not the grid is up. A 48-hour stock is empty at the start of day 2. This is the engine's fuel-draw convention; a dispatch-aware fuel draw is deferred to v1.1, and batteries are deferred with it because the solver has no dispatch order.
Tiers and the military reserve
Workloads sit in three tiers: Military reserve, Critical civil, Commercial. The solver serves tiers in rank order and locks each tier's allocation before serving the next. Each data center sets aside a percentage of its compute as military reserve; only Military reserve workloads can use it, and idle reserve is not given to lower tiers. A workload marked monolithic must be served from one site; the solver tries each site's reserve and reports the shortfall if none can hold it.
The tier bar shows the percentage of a tier's workloads whose overall service is at least half of demand. It is a headcount of workloads, not a percentage of demand met, and a workload with a critical data dependency counts as unserved when its data is cut even if its compute was allocated. The per-workload table shows compute allocated, data delivered and overall service separately, and they are different things.
What the numbers mean
Compute allocated is what the solver assigned; delivered data is what reached the delivery point; overall service is the minimum across the workload's critical dependencies.
The modeled grid imports use SIMULATED tie-line capacities and the published national generation mix. When stored LNG runs out, the model removes the gas-fired share. Assuming the rest of Taiwan can still supply the full non-gas share to Tainan is an upper bound. The import sources are editable assets; a facilitator can change their capacities and rerun.
What the model does not do
It does not dispatch. It does not model frequency, inertia, black start, restart clocks at fabs, or anything shorter than a day. It does not infer dependencies you did not draw. Lines are bidirectional. A reachable source is capability, not metering. Damage and repair magnitudes are ILLUSTRATIVE until an asset carries a cited value. Dependency Analysis is a read-only SIMULATED full-outage sweep of nodes, one at a time, on the day you are viewing.
Downloads
Everything below is unclassified and labeled with where its numbers come from. Each file has a SHA-256 sidecar for checking the download.
Tainan scenario workbooks
The two embedded layouts are available as scenario workbooks, Sun Ba II excluded: Consolidation and Fragmentation. Import either through Scenario Workbook to load that layout. Row source fields preserve citations and SIMULATED flags.
Download Consolidation · SHA-256
Download Fragmentation · SHA-256
Plays
Twelve scenario workbooks, six per layout, each the baseline plus one change: 01 Blockade (both LNG import lanes cut at day 1), 02 Nanke (345 kV substation outage at day 1), 03 Fangshan (cable landing cut at day 1), 04 CarrierHotel (service loss at day 1), 05 Gateway (satellite link damage at days 2 and 9), 06 Islanding (science park PCC open days 5 to 19). Files are named Consolidation-NN-Name.xlsx and Fragmentation-NN-Name.xlsx under /circuit/files/. Import one to run it; the terminal treats it as a complete scenario. Outages are generic functional-loss rows; weapon-specific and cyber effects are not pre-authored.
Consolidation
Fragmentation
How to cite this work
Dodge, B. (2026). CIRCUI-T: Compute Infrastructure Resilience under Contested Utilities and Interdiction - Taiwan. Independent student research, Cyber/AI program, U.S. Naval War College.
Questions a skeptic asks
Is this official DoD policy?
No. This site presents independent student research conducted as part of the Cyber/AI program at the United States Naval War College. It does not represent the official position of the Naval War College, the U.S. Navy, the Department of Defense, or the U.S. Government.
Are the data centers real?
In the Tainan scenarios the plants, stations and lines come from OpenStreetMap and public sources; every data center, service delivery point and connection assumption is SIMULATED and says so in its source field.
Does it predict what will happen to Taiwan?
CIRCUI-T does not predict what will happen to Taiwan. It shows, for a stated set of assumptions, which dependencies bind first and how a layout changes that. The assumptions are listed, flagged and editable. Change one in the terminal and the answer changes with it, and the scenario ledger records what you changed.
Where does my work go?
The Tainan scenarios are larger than this browser's local storage can hold, so autosave is unavailable for them and the terminal says so; export a workbook before you leave or reload. Smaller scenarios autosave to local storage in plaintext. CIRCUI-T does not upload scenario content. Local storage and exported workbooks are not encrypted and may become sensitive when populated. Handle them under local guidance.